Utah FORGE: Well 16B(78)-32 Drilling Data
This drilling data for Utah FORGE well 16B(78)-32 include a well survey, core summary, mud and mud temperature logs, daily reports of the drilling process, and additional data from the Pason oil and gas company. Well 16B(78)-32 serves as the production well for reservoir creation, fluid circulation, and demonstration of heat extraction for the FORGE project. It has been drilled as a doublet approximately 300 feet parallel to and above the injection well 16A(78)-32. The proposed total depth was 10,658 feet, which was exceeded. Spudding began on April 26th, 2023. As of June 20th, 2023, the total depth measured 10,947 feet and the vertical depth measured 8,357 feet.
Drilling included the trial use of insulated drill pipe (IDP) from Eavor Technologies, which was considered a success. IDP restricts counter-current heat transfer between drilling fluid inside the drill string and hotter returning fluid in the annulus, thereby ensuring the bottomhole assembly (BHA) remains submerged in cool fluid. Eavor rented 350 joints of IDP to FORGE which were run in two consecutive BHAs at the well. The results of this trial are included here.
Citation Formats
Energy and Geoscience Institute at the University of Utah. (2023). Utah FORGE: Well 16B(78)-32 Drilling Data [data set]. Retrieved from https://dx.doi.org/10.15121/1998591.
McLennan, John, Mock, Blake, Swearingen, Leroy, Baldwin, Randy, Hodder, Mark, Vetsak, Alex, Kuhns, A.T., Breland, Jack, and England, Kevin. Utah FORGE: Well 16B(78)-32 Drilling Data. United States: N.p., 03 Jul, 2023. Web. doi: 10.15121/1998591.
McLennan, John, Mock, Blake, Swearingen, Leroy, Baldwin, Randy, Hodder, Mark, Vetsak, Alex, Kuhns, A.T., Breland, Jack, & England, Kevin. Utah FORGE: Well 16B(78)-32 Drilling Data. United States. https://dx.doi.org/10.15121/1998591
McLennan, John, Mock, Blake, Swearingen, Leroy, Baldwin, Randy, Hodder, Mark, Vetsak, Alex, Kuhns, A.T., Breland, Jack, and England, Kevin. 2023. "Utah FORGE: Well 16B(78)-32 Drilling Data". United States. https://dx.doi.org/10.15121/1998591. https://gdr.openei.org/submissions/1516.
@div{oedi_1516, title = {Utah FORGE: Well 16B(78)-32 Drilling Data}, author = {McLennan, John, Mock, Blake, Swearingen, Leroy, Baldwin, Randy, Hodder, Mark, Vetsak, Alex, Kuhns, A.T., Breland, Jack, and England, Kevin.}, abstractNote = {This drilling data for Utah FORGE well 16B(78)-32 include a well survey, core summary, mud and mud temperature logs, daily reports of the drilling process, and additional data from the Pason oil and gas company. Well 16B(78)-32 serves as the production well for reservoir creation, fluid circulation, and demonstration of heat extraction for the FORGE project. It has been drilled as a doublet approximately 300 feet parallel to and above the injection well 16A(78)-32. The proposed total depth was 10,658 feet, which was exceeded. Spudding began on April 26th, 2023. As of June 20th, 2023, the total depth measured 10,947 feet and the vertical depth measured 8,357 feet.
Drilling included the trial use of insulated drill pipe (IDP) from Eavor Technologies, which was considered a success. IDP restricts counter-current heat transfer between drilling fluid inside the drill string and hotter returning fluid in the annulus, thereby ensuring the bottomhole assembly (BHA) remains submerged in cool fluid. Eavor rented 350 joints of IDP to FORGE which were run in two consecutive BHAs at the well. The results of this trial are included here.}, doi = {10.15121/1998591}, url = {https://gdr.openei.org/submissions/1516}, journal = {}, number = , volume = , place = {United States}, year = {2023}, month = {07}}
https://dx.doi.org/10.15121/1998591
Details
Data from Jul 3, 2023
Last updated May 21, 2024
Submitted Sep 6, 2023
Organization
Energy and Geoscience Institute at the University of Utah
Contact
John McLennan
801.587.7925
Authors
Keywords
geothermal, energy, well 16B78-32, Utah FORGE, well 16B78-32 drilling, well 16B78-32 drilling data, drilling data, Utah FORGE drilling data, well 16B78-32 drilling logs, well 16B78-32 logs, well 16B78-32 daily reports, well 16B78-32 survey, Utah FORGE drilling, core drilling, core, Pason, Pason data, mud temperature logs, mud temperature, daily reports, core summary, Eavor, insulated drill pipe, insulated drill pipe test, Utah geothermal, mud logs, lithology, geologyDOE Project Details
Project Name Utah FORGE
Project Lead Lauren Boyd
Project Number EE0007080