This is the first project report and induced seismicity mitigation plan for the Newberry Enhanced Geothermal Systems (EGS) Demonstration project. The primary objectives of this first phase were to obtain necessary permits and comply with all regulations, including NEPA, communicate with the public, regulators and other stakeholders, develop a geologic model by evaluating current geoscience data and characterizing existing wells, supplemented by additional injection test and wellbore survey information, and formulate a detailed stimulation plan for the following project phases. Also attached here are reports on the successive stimulation phases of the project.

Citation Formats

TY - DATA AB - This is the first project report and induced seismicity mitigation plan for the Newberry Enhanced Geothermal Systems (EGS) Demonstration project. The primary objectives of this first phase were to obtain necessary permits and comply with all regulations, including NEPA, communicate with the public, regulators and other stakeholders, develop a geologic model by evaluating current geoscience data and characterizing existing wells, supplemented by additional injection test and wellbore survey information, and formulate a detailed stimulation plan for the following project phases. Also attached here are reports on the successive stimulation phases of the project. AU - Cladouhos, Trenton A2 - Petty, Susan A3 - Iovenitti, Joe A4 - Callahan, Owen A5 - Osborn, William A6 - Nofziger, Laura A7 - Sonnenthal, Eric DB - Geothermal Data Repository DP - Open EI | National Renewable Energy Laboratory DO - KW - geothermal KW - energy KW - newberry KW - EGS KW - demonstration KW - volcano KW - AltaRock KW - Oregon KW - geology KW - geologic model KW - conceptual resource model KW - seismicity KW - induced seismicity KW - mitigation KW - maximum magnitude KW - in situ stress KW - permitting KW - stimulation KW - reservoir characterization KW - drilling plan KW - well testing KW - risk mitigation KW - reporting LA - English DA - 2024/05/05 PY - 2024 PB - AltaRock Energy Inc T1 - Newberry EGS Demonstration: Initial Project Report and Induced Seismicity Mitigation Plan, 2011 UR - https://gdr.openei.org/submissions/1599 ER -
Export Citation to RIS
Cladouhos, Trenton, et al. Newberry EGS Demonstration: Initial Project Report and Induced Seismicity Mitigation Plan, 2011. AltaRock Energy Inc, 5 May, 2024, Geothermal Data Repository. https://gdr.openei.org/submissions/1599.
Cladouhos, T., Petty, S., Iovenitti, J., Callahan, O., Osborn, W., Nofziger, L., & Sonnenthal, E. (2024). Newberry EGS Demonstration: Initial Project Report and Induced Seismicity Mitigation Plan, 2011. [Data set]. Geothermal Data Repository. AltaRock Energy Inc. https://gdr.openei.org/submissions/1599
Cladouhos, Trenton, Susan Petty, Joe Iovenitti, Owen Callahan, William Osborn, Laura Nofziger, and Eric Sonnenthal. Newberry EGS Demonstration: Initial Project Report and Induced Seismicity Mitigation Plan, 2011. AltaRock Energy Inc, May, 5, 2024. Distributed by Geothermal Data Repository. https://gdr.openei.org/submissions/1599
@misc{GDR_Dataset_1599, title = {Newberry EGS Demonstration: Initial Project Report and Induced Seismicity Mitigation Plan, 2011}, author = {Cladouhos, Trenton and Petty, Susan and Iovenitti, Joe and Callahan, Owen and Osborn, William and Nofziger, Laura and Sonnenthal, Eric}, abstractNote = {This is the first project report and induced seismicity mitigation plan for the Newberry Enhanced Geothermal Systems (EGS) Demonstration project. The primary objectives of this first phase were to obtain necessary permits and comply with all regulations, including NEPA, communicate with the public, regulators and other stakeholders, develop a geologic model by evaluating current geoscience data and characterizing existing wells, supplemented by additional injection test and wellbore survey information, and formulate a detailed stimulation plan for the following project phases. Also attached here are reports on the successive stimulation phases of the project.}, url = {https://gdr.openei.org/submissions/1599}, year = {2024}, howpublished = {Geothermal Data Repository, AltaRock Energy Inc, https://gdr.openei.org/submissions/1599}, note = {Accessed: 2025-05-11} }

Details

Data from May 5, 2024

Last updated Jul 9, 2024

Submitted May 5, 2024

Organization

AltaRock Energy Inc

Contact

Trenton Cladouhos

206.605.1948

Authors

Trenton Cladouhos

AltaRock Energy

Susan Petty

AltaRock Energy

Joe Iovenitti

AltaRock Energy

Owen Callahan

AltaRock Energy

William Osborn

AltaRock Energy

Laura Nofziger

AltaRock Energy

Eric Sonnenthal

Lawrence Berkeley National Laboratory

DOE Project Details

Project Name Newberry EGS Demonstration

Project Lead Lauren Boyd

Project Number EE0002777

Share

Submission Downloads